Central Office Rewire & Upgrade
Electrical Finished Project
Central Office Rewire & Upgrade
A three-floor office rewired with a new distribution board, labelled circuits and emergency lighting — certified safe and handed over a day early.
- Duration
- 10 working days
- Crew
- 2 electricians
- Materials
- New consumer unit, LED panels
- Guarantee
- 5-year electrical certificate
On Site How It Went
From First Visit To Final Wipe-Down
Thirty staff, three floors and wiring from the nineties — breakers tripped weekly and nobody knew which switch fed which room. We surveyed every circuit after hours, then rewired floor by floor so the business never lost a working day.
A new consumer unit with labelled circuits and surge protection anchors the system, LED panels cut lighting load by half, and emergency lighting now covers every escape route. The test certificates and a laminated circuit chart went into the office file — and we finished a full day early.
Step By Step The Work Plan
Exactly What We Did
After-hours survey: every circuit traced, mapped and load-tested.
Floor-by-floor rewire: new cabling pulled over evenings and weekends.
New consumer unit: labelled board, surge protection and LED panels throughout.
Certify and handover: test certificates, circuit chart and staff walkthrough.
"Zero downtime across three floors of staff. The labelled board alone is worth it — our facilities team finally knows what feeds what."